2010 Street Rehabilitation (MFT) ProgramResidents in affected areas will receive a hand-delivered flyer before work begins describing the process and providing details. If you have any questions or concerns, please feel free to contact
|
Related Documents
|
| Overview: | Annual pavement rehabilitation and repair program. | ||||||||||||||||||||||||
| Status: |
Week of August 16th Week of August 9th Week of August 2nd Week of July 26th
Week of July 12th Week of July 5th Week of June 28th The proposed street rehabilitation and underground utility repair locations are as follows:
The scope of the project includes repairs to the existing storm and sanitary sewer systems, and water main appurtenances in addition to the proposed street rehabilitation work. This project has been divided into three phases to facilitate the completion of the project in a timely manner and with as little disruption to residents as is possible. Phase I: The first phase involves underground utility repair work. Please note that all work will be performed within the City right-of-way. If you have any type of existing features within the City right-of-way area (i.e. sprinkler system, landscape features, special decorative rocks, brick driveways, electronic “invisible” dog fence, etc.) or any other specialty items precautions should be taken by you, the homeowner, to remove or store these items right away to assure that no damage occurs to these specific items. The City will not repair or replace private appurtenances left within the City right-of-way. Phase II: Once Phase I has been completed the second phase of construction which involves street rehabilitation work will begin. This construction phase includes the following work:
Phase III: The third phase will involve parkway restoration. All areas disturbed by construction will be restored and residents advised in writing as to recommended sod maintenance. We are planning the completion of all three phases of this contract to be completed by September 15, 2010. During construction, for short periods of time, homeowners may not have access to their driveways or the street. This is required for access to the various utilities, pavement grinding, tack coat application and pavement resurfacing work. In these instances, residents will be notified as to dates and times for removal of personal vehicles by street posting and/or notification letters. We intend to give as much notice as possible in these situations in an effort to lessen the negative impact to homeowners. Driveway Apron Restoration: The City is also proud to announce that this will be the first year that the City of St. Charles will offer to its residents the opportunity to have their driveway aprons replaced completely rather than the standard repair of approximately three feet from the edge of pavement that has been utilized in the past. This is a one-time opportunity for the homeowners to purchase this additional work at the contract bid price. What the City will be requiring from all residents who are interested in this program is to complete the attached request form and return it to the City with a check, for full payment, by June 1, 2010. This will allow ample time for staff to prepare a list for our contractor as well as to have these areas corrected as part of the overall program.
|